Launch readiness checklist for an e-bike station

What should be true before the first rider signs up, in 16 checks across the station, the bikes, the riders and the host.

For: Hosts preparing for launch week, property managers and campus offices

A rose ribbon stretched across a path in front of a new bike station, with a pair of scissors resting on a small stool beside it.

Checklist

Tick items as you confirm them. Progress stays on this page only; download the list when you are done.

Station
Bikes
Riders
Host

0 of 16 items confirmed

Launch week is the fourth of six stages in how Colibrino works: site walk, network plan, install, launch week, operate and season review. By the time the first rider signs up, the station should be installed and inspected, every bike checked and charged, riders told how it works, and the host clear on what happens next. This checklist has 16 items in four groups to confirm all of that before opening day.

How to use the checklist

Go through it with the host contact in the days before launch week. Tick each item that is confirmed; the counter shows how many of the 16 are done. Print it or download it as a CSV file and keep it with the installation and inspection record. Anything unticked becomes a task with a name and a date beside it.

Station (4 items)

  • The station is installed, anchored and inspected.
  • Every bay charges and locks, tested one by one rather than as a sample.
  • Signs show how to unlock, ride, return and get help.
  • The circuit has run at full charging load without tripping. In the fictional Larkspur Commons example, that means 8 bikes drawing 800 W together on one 20-amp, 120-volt circuit; the station power calculator shows the numbers for your own station.

Bikes (4 items)

  • Every bike passed a full safety check and a test ride.
  • Every bike and battery serial number is recorded, which also makes recall checks possible; the battery safety checklist covers those.
  • Every battery is charged before launch day.
  • Spare parts and one spare bike are on hand.

Riders (4 items)

  • Residents or students received the launch notice and the rules. The community e-bike rules builder gives a starting draft.
  • Sign-up and unlock were tested, start to finish, by someone who has never seen the system. A newcomer finds the confusing step that the people who set it up no longer notice.
  • The support phone and email are posted on the station and in the notice.
  • A short safety session is scheduled for launch week.

Host (4 items)

  • The host contact knows who to call, and what to expect after calling.
  • Maintenance and snow crews know where the station is.
  • The first monthly report date is set.
  • A review meeting is booked for the end of the first season.

Example (fictional). At Larkspur Commons, a fictional 240-home apartment community, the network plan is delivered on day 12, the install and inspection happen on day 34, and launch week runs from day 35 to day 41 with two safety sessions. The season review on day 90 recommends keeping both stations and adding a third near the pool next season. The full timeline is on the example network page.

What launch week includes

In a Colibrino program, launch week brings a launch notice, rider rules and a safety session, and the support contacts go up on the station. The written record before it is the installation and inspection record. After it comes the monthly ride report, with trips, active riders, bike availability, and issues and fixes. See rider support and training and ride data and reporting.

Reading your result

Some items can slip a day without harm, such as the review meeting. Others should hold the launch: an untested bay, a circuit that has not carried full load, or a bike that has not passed its safety check. If any of those is unticked, move the opening date rather than open on time.

Limits

The checklist confirms readiness. It does not replace the electrician’s sign-off, the installer’s inspection or any approval the location needs.

What to do next

See the full sequence on how we work. If you are not at this stage yet, start with the site assessment checklist, or plan a station to book a site walk.

Start with one station.

Tell us about the place: how many homes or beds, where people come and go, and where the nearest outlet is. We reply with questions or a time to walk the site with you.